Hastings Street water main engineering contract with Mackie Consultants

You are reading edition 2, an earlier version of this page. Read the current edition.

On March 4, 2024 the City Council approved, on its consent agenda, a contract with Mackie Consultants for Hastings Street water main engineering services, including design and construction inspection, in the amount of $64,605. The staff memo and evaluation sheet identify the request for proposals as PW-24-06 and report that Mackie scored highest, although it was not the lowest-cost proposal; the agenda item printed a different number. The roll call was 6–0. Source: draft minutes.

Documented status: Awarded (recorded in draft minutes), Mar 4 2024. Evidence dated .

Official identifiers: PW-24-06

What changed, and when did it take effect?

  1. · Awarded · Recorded in draft minutes

    City Council approves the contract

    Meeting date: Mar 4 2024. Contract value: $64,605 for services; counterparty: MACKIE CONSULTANTS. Item VI: the motion carried (6 to 0, 1 absent). Consultant: MACKIE CONSULTANTS.

    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.
    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.
    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.
    • p. 1 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.

What was requested, recommended, approved, contracted, reported paid and completed?

  • Contract value · Mar 4, 2024

    $64,605

    Services

    MACKIE CONSULTANTS (contractor)
    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.

Contracts, payments and completion

  1. · Awarded · Recorded in draft minutes

    City Council approves the contract

    Meeting date: Mar 4 2024. Contract value: $64,605 for services; counterparty: MACKIE CONSULTANTS. Item VI: the motion carried (6 to 0, 1 absent). Consultant: MACKIE CONSULTANTS.

    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.
    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.
    • p. 2 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.
    • p. 1 · Draft minutes of City Council - March 4, 2024 (Draft Minutes), City Council, Mar 20 2024. Open the quote and source.

Which parcels, agencies, businesses and projects are explicitly connected?

Organizations and public bodies

What remains unresolved?

  • Open

    seven (7) sealed proposals were received

    • p. 1 · Staff memo of Approve a contract for Hastings Watermain Engineering Services, PW-26-04, with Mackie Consultants in the amount of $64,605.00 (Memorandum), City Council, Mar 4 2024. Open the quote and source.

Open questions

No open question is recorded for this item.

What does the evidence suggest, and what would change it?

No conflicting records are published for this item.

Official source records

  1. City Council - March 4, 2024 (Draft Minutes)

    City Council, Mar 20 2024

  2. Approve a contract for Hastings Watermain Engineering Services, PW-26-04, with Mackie Consultants in the amount of $64,605.00 (Memorandum)

    City Council, Mar 4 2024

Editions and corrections

Each published change is a new edition. Corrections say what changed and why.

  1. Edition 3(current)

    Edition 3: 2 revised.

  2. Edition 2(shown on this page)

    Edition 2: 2 revised.

  3. Edition 1Read this edition

    First edition.

Editorial responsibility: Parcel Thread. Updated . Independent research; not affiliated with a government agency.

Suggested citation: Parcel Thread, “Hastings Street water main engineering contract with Mackie Consultants,” updated 2026-09-25, source records listed on this page.

Initial permanent evidence page published September 10, 2026.

About this data

Amounts and statuses come from the cited pages; a recommended, awarded or authorized amount is not a payment.

Confirm condition deadlines with the City before relying on them.