Park Ridge · Contract award
Purchase order increase for the Cumberland watermain replacement
You are reading edition 2, an earlier version of this page. Read the current edition.
The staff memo reports the project was approved at $2,235,000 and that unforeseen conditions led to change orders and added quantities. The contractor is not named in the memo. The roll call was 7–0. Source: draft minutes.
Documented status: Amended (recorded in draft minutes), Feb 5 2024. Evidence dated .
What changed, and when did it take effect?
· Amended · Recorded in draft minutes
City Council approves the purchase order increase
Meeting date: Feb 5 2024. Item VI: the motion carried (7 to 0).
p. 3 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
p. 1 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
What was requested, recommended, approved, contracted, reported paid and completed?
Contract value
$2,235,000
Construction
p. 1 · Staff memo of Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum), City Council, Feb 5 2024. Open the quote and source.
Contracts, payments and completion
· Amended · Recorded in draft minutes
City Council approves the purchase order increase
Meeting date: Feb 5 2024. Item VI: the motion carried (7 to 0).
p. 3 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
p. 1 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
Which parcels, agencies, businesses and projects are explicitly connected?
No explicit connection is published for this item.
What remains unresolved?
Open
Several unforeseen circumstances were encountered resulting in change orders and additional quantities
p. 1 · Staff memo of Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum), City Council, Feb 5 2024. Open the quote and source.
Open questions
No open question is recorded for this item.
What does the evidence suggest, and what would change it?
No conflicting records are published for this item.
Official source records
Editions and corrections
Each published change is a new edition. Corrections say what changed and why.
Edition 3(current)
Edition 3: 2 revised.
Edition 2(shown on this page)
Edition 2: 2 revised.
Edition 1Read this edition
First edition.