Purchase order increase for the Cumberland watermain replacement

You are reading edition 2, an earlier version of this page. Read the current edition.

The staff memo reports the project was approved at $2,235,000 and that unforeseen conditions led to change orders and added quantities. The contractor is not named in the memo. The roll call was 7–0. Source: draft minutes.

Documented status: Amended (recorded in draft minutes), Feb 5 2024. Evidence dated .

What changed, and when did it take effect?

  1. · Amended · Recorded in draft minutes

    City Council approves the purchase order increase

    Meeting date: Feb 5 2024. Item VI: the motion carried (7 to 0).

    • p. 3 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
    • p. 1 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.

What was requested, recommended, approved, contracted, reported paid and completed?

  • Contract value

    $2,235,000

    Construction

    • p. 1 · Staff memo of Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum), City Council, Feb 5 2024. Open the quote and source.

Contracts, payments and completion

  1. · Amended · Recorded in draft minutes

    City Council approves the purchase order increase

    Meeting date: Feb 5 2024. Item VI: the motion carried (7 to 0).

    • p. 3 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.
    • p. 1 · Draft minutes of City Council - February 5, 2024 (Draft Minutes), City Council, Feb 20 2024. Open the quote and source.

Which parcels, agencies, businesses and projects are explicitly connected?

No explicit connection is published for this item.

What remains unresolved?

  • Open

    Several unforeseen circumstances were encountered resulting in change orders and additional quantities

    • p. 1 · Staff memo of Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum), City Council, Feb 5 2024. Open the quote and source.

Open questions

No open question is recorded for this item.

What does the evidence suggest, and what would change it?

No conflicting records are published for this item.

Official source records

  1. City Council - February 5, 2024 (Draft Minutes)

    City Council, Feb 20 2024

  2. Approve a Budget Amendment and Purchase Order Increase to the Water Construction Account in the Amount of $139,000 for the Cumberland Watermain Replacement Project (Memorandum)

    City Council, Feb 5 2024

Editions and corrections

Each published change is a new edition. Corrections say what changed and why.

  1. Edition 3(current)

    Edition 3: 2 revised.

  2. Edition 2(shown on this page)

    Edition 2: 2 revised.

  3. Edition 1Read this edition

    First edition.

Editorial responsibility: Parcel Thread. Updated . Independent research; not affiliated with a government agency.

Suggested citation: Parcel Thread, “Purchase order increase for the Cumberland watermain replacement,” updated 2026-09-25, source records listed on this page.

Initial permanent evidence page published September 10, 2026.