FundedWillow Road reconstruction moves to November
A July update shifts expected construction to November 2026 and connects road rebuilding with storm sewer, watermain and sanitary-sewer work.
Funded project; start anticipated November 2026
Status as of Jul 13, 2026Willow Road, east of Forestway Drive to Provident Avenue; Hibbard intersection
Decision → work → effects
The decision
What the record says
Fund and reschedule coordinated works
The Village identifies a federal transportation grant and IDOT cost-sharing agreement.
What changes
The action or work involved
Rebuild road and renew utilities
Project includes Willow Road, nearby Hibbard segments, a new storm sewer, watermain replacement and sanitary-sewer improvements.
What follows
Effects on the neighborhood
Temporary disruption near schools and businesses
The Village warns of disruptions to residents, schools and local businesses; precise detours are not yet established.
Documented means stated in a linked source. Possible effects are conditional interpretations. A proposed or planned action is not an approval or a guaranteed outcome.
What to watch next
Next step
Check the construction notice for actual start, detours, utility interruptions and school access arrangements.
Decision timeline
Jul 13, 2026
Schedule revised
The earlier late-spring target changed to November, weather permitting.
November 2026
Expected construction start
Anticipated, not confirmed.